2.4.2 System Wiring
The connection and wiring procedure for C-BOX 100 is described as follows:
1) Open the C-BOX 100 as described in paragraph 2.2.
2) Verify that the C-BOX 100 power switch is off (see Figure 6).
3) Unscrew the compression connectors and pass all the system cables
through them into the C-BOX 100 housing.
4) To connect the power and input/output signals:
Prepare the individual wires of the system cables by stripping the
insulation back approximately 1 cm.
Using a device such as a screwdriver, push down on the lever directly
next to the clamp (see Figure 8).
Insert the wire into the clamp and release the lever.
The wire will now be held in the spring clamp.
Figure 8 - System Cable Connections
The wiring used can be solid or stranded but must meet the following specifications.
All positions: 24 - 16 AWG 0.2 - 1.5 mm²
The C-BOX 100 spring clamp connector pinouts are indicated in the following table.
Refer to the scanner Installation Manual for details.